The Boardwalk Shopping Centre
Project completion
July 2023
Location
Portsmouth
Project brief
Prestec have recently completed a project for valued client Workman LLP, we were asked to provide assistance with collapsed paving and kerb lines, the site being a previous landfill facility 30 years ago. We excavated and remediated the sub base, new kerbs, construction of new concrete foundation for access ramps, new brick ramp walls, followed by lift and relay 300m2 of block paving.
Services utilised



Similar projects
Take a look at some of our other projects below

Project Instruction Home of Harry Potter’s Parents
Project Duration
12 weeks
Location
Wiltshire

Office & Warehouse Refurbishment – Gravelly Industrial Park
Project completion
December 2024
Location
Birmingham