Eggington Hall, Park Hill, Derby
Job Completion
May 2016
Client
Acorn Care and Education Limited
Duration
12 weeks
Project Brief
Prestec have completed a successful handover of Phase one of the £250,000 fast-track refurbishment at Eggington Hall, near Derby. The works comprised of the refurbishment of the premises to form a Special Needs School for Acorn Care & Education Limited.
The project was due to be carried out in phases and the first phase was completed on 24th March 2015, in time for the clients Ofsted inspection.
Acorn Care & Education Ltd were extremely pleased to receive a clean bill of health from the inspection and subsequently released a second phase of the works to Prestec UK, with an immediate start.
Phase two will continue with the refurbishment of further rooms, including the music room, art room, science classroom, catering classroom and the toilets. Further alterations will include, decoration, new flooring, electrical and heating upgrades, new fire and security alarms and secondary glazing will be completed.
Services Utilised

"Prestec have completed our works to a very high standard and have been a pleasure to work with. With the nature of our Kids we demand a high level of professionalism at our Schools of which all of the employee’s and Sub-contractors from Prestec have been from the very beginnings of the build."
Paul Platt
FM Project Manager, Acorn Care & Education
Similar Projects
Take a look at some of our other projects below.

Project Instruction Home of Harry Potter’s Parents
Project Duration
12 weeks
Location
Wiltshire

Office & Warehouse Refurbishment – Gravelly Industrial Park
Project completion
December 2024
Location
Birmingham